Civil / Structural
Engineer
Construction of 105 MMSCFD Hydrogen Plant (Edmonton 2)
Canada, 2006 January – Air Products and Chemicals Inc. (APCI) announce to construct a 105
million standard-cubic-feet-per-day (MMSCFD) hydrogen production plant expected to serve by April 2008 to several customers
in the Alberta Heartlands industrial corridor and the Petro-Canada refinery which will be the first in Canada to provide a sale of hydrogen for use
in the upgrading of Canadian oil sands. This is the second facility to be constructed by Air Products in alliance with Technip
USA to supply hydrogen to Petro-Canada's 135,000 barrel per day refinery,
as well as several additional customers in the Edmonton area.
Engineering activities
¨ Design and review of various civil
and structural items that includes:
1. Combustion air and flue gas duct works
2. Lifting schemes for Structural Steel modules
3. Open frame steel structure and supports
4. Laying out of platforms and walkways
¨ Participate in the model review to
ensure civil items proper clearance with piping, electrical, furnace and mechanical equipments through smart plant and plant
design (PDS) to satisfy OSHA and project requirements.
¨
Assisted
in the review of fabrication drawings.
Civil Engineer
Construction of Container Berth and Stacking Yard, Pasir Panjang Terminal
(Phase C06 to C08)
Singapore, 2005 March – Ports of Singapore Authority (PSA) awards to TOA Corporation the
Phase C06 to C08 project, which costs S$76 million. The three-berth expansion project expected early 2007 is to be completed
phase by phase and will be handed over to PSA immediately for operation. Major activities are piling onshore, rock protection
works, pre-cast beam and slabs assembly, stacking yard pavement and installation of port ancillaries that includes gantry
cranes.
Pasir Panjang Terminal (PPT) is Singapore’s newest state-of-the-art and most advanced container
terminal. From its quay cranes that can handle the largest containerships, its towering bridge cranes for yard operations,
through to its paperless flow-through gate.
Engineering activities
¨
Reviewed applicability
of existing construction drawings, defined and recommended appropriate changes as proposed alternatives to resolve identified
interface among ancillaries, openings and connections of piles, precast slabs and beams. Presented and discussed with the
client thru meetings for verification and approval.
¨
Part of the team
in the planning and preparation of execution plan for the following activities:
1. Piling sequence (percussion and auger method)
2. Sand filling and revetment works
3. Construction of caisson deck
¨ Assisted in the preparation and drafting of various
technical drawings such as piling plan (966 marine 1m dia. spun piles), detailed shop drawing layout plan and detail of technical
proposals.
Civil Engineer
Reclamation At Pulau Ubin & Pulau Tekong Project (Part 1)
In October 2000, Partners TOA Corporation and Jan De Nul commenced the 1,400-hectare of land reclamation
project at Pulau Ubin and Pulau Tekong, Singapore. This massive project for housing and residential purposes involves the
filling of 200 million m³ of sand, capital dredging of waterways, the construction of an offshore dumping ground for disposal
of 24 million m³ of soft clays, the construction of a staging area on the mainland using 6 million m³ of good earth and 3.5
million m³ of clay and bund construction area length of 15 km. The project, being worth S$1.84 billion, is suppose to
be completed November of 2005 however due to unforeseeable circumstances the project is still in progress and is expected
to last until 2007 indefinitely.
Engineering activities
¨
Arranged and prepared
various design calculations that includes a temporary jetty, structural serviceability of an existing bridge, slope stability
checks, soil improvement and lined drains for the entire reclamation area.
¨
Conducted site
visits to investigate actual site conditions that may require further analysis and review considering various aspects such
as slope stability, settlement, and erosion. Recommends appropriate solutions with supporting technical data to ensure works
as per design and safe completion of construction activities.
¨
Estimation of all
quantities for various civil structures and other reclamation quantities with complete detailed breakdown in support to the
contracts department for preparation of claims to client.
¨
Organized and prepared
detailed proposals on connections and transitions with design, quantities and illustrations not included in the original contract.
Achieved objectives of the project, technical and aesthetic quality and cost effective designs. Prepared detail of construction
drawings that include layout plans, sectional details and views of various reclamation items.
Management
¨
Attended numerous
meetings with client to confirm and settle inquiries on the submitted designs, construction drawings, proposals and quantities.
Maintained and updated tracking record list of ongoing items with history to monitor progress and served as a guide and reference
in the meetings.
¨
Obtained endorsement
of design calculations and detail drawings from local professional engineers as a requirement by the client.
¨
Deputised for other
engineers, appropriate to his functional work, when required. Supervised and maintained timely schedule of dispersed designs
and workloads.
¨
Assisted in other
projects on special assignment basis that require expertise in civil design, technical proposal building, AutoCAD and Terramodel
applications.
¨
Provided support
in the handling of document records, procedures and filing as per ISO 9001 standard requirements in anticipation for future
audit.
Civil / Structural Supervisor
BPC Polyethylene Plant Project
The polyethylene plant project commenced in December 1997 at the Petrochemical Park, Bataan, Philippines, owned
by a consortium led by British Petroleum, Petronas Berhad of Malaysia and some local investors. This project worth U$150-million
completed in March 2000 involves heavy lifting and construction of temporary jetty for the unloading of two gigantic reactors,
construction of four super structures, numerous pipe bridges, huge foundations for tanks, flare stack, and buildings &
structure, platforms, walkways, roads, and various structures.
The plant is estimated to run at a capacity of 275,000 metric tons per year and started commercial production
in 2000. It is to produce polyethylene resins in the form of white pellets, which are used as raw materials for PET bottles,
films, monobloc chairs, PVC pipes and other applications.
Engineering activities
¨ Attended coordination meetings to discuss,
clarify and develop cost effective and fit for purpose design solutions to fit project requirements to various engineering
and technical issues and problems as well as progress of works and other pertinent matters with other contractors.
¨ Reviewed and prepared field design
changes, replied to technical inquiries and directly supplied solutions backed by design calculations if necessary thru site
instructions to the contractors for its immediate action and implementation.
¨ Reviewed applicability of existing
drawings, Standards and Specifications and recommend appropriate changes. Where appropriate, carried out basic surveying work
sufficient to meet the design needs.
¨ Evaluated and approved external contractors
claims for field changes and variations with cost. Coordinated
with project engineering group for drawings, specifications, clarifications, progress reports, progress/final claims of contractors/consultants,
procurement of critical items, contract administration, variations, action items, interfaces, handing over etc.
Management & Supervision
¨ Assisted in carrying out duties and
responsibilities for the planning, coordination, timely completion and safe execution of site works to lead civil structural
group in the entire course of the project execution.
¨ Carried out regular monitoring thru
visits and inspections of work sites of all operations in progress to establish existing conditions, ensure safe working premises
and practices. Takes proactive measures and strict follow
up for mitigation of impact of any delays/constraints affecting progress of works. Anticipates, forecasts and highlights areas
of concern to the department head and recommends for improvements.
¨ At completion, arranged and issued
to contractors punch list of major structures then performed final inspection, ensuring all items identified in the list are
satisfied and complied accordingly prior to handing over.
¨ Reviewed documents received from contractors/consultants such as
organization chart, equipment/manpower mobilization programme, construction programme, structural steel erection procedures, shop drawings, QA/QC & HSE plan, ensured their implementation, took necessary action in cases
of any lapse and/or lagging.
¨ Coordinated site control procedures such as progress reporting, man
hours, down times, site supervision, QA/QC, HSE, work permits.
¨ Attended meetings with contractors, consultants, and vendors to review
progress on weekly basis. Analysed and addressed critical areas of progress/delays in construction, procurement, resource
mobilization and any other areas shortcomings. Reviewed and acknowledged minutes of the meetings.
Project Coordinator
BPC Polyethylene Plant Project
Engineering activities
¨ Checked and processed detailed calculations, design
drawings and fabrication drawings for approval set for release to the client. Ensured the application of design codes, standards,
practices and specifications.
¨ Re-designed and modified design calculations
on urgent basis such as sudden change of loadings and vendor details, on-site modifications or by the remarks received from
consultant and client.
¨ Review/comment on the detailed design
calculations and drawings submitted by contractors and consulting engineers. Ensured consistency with the latest information.
Modified calculations and drawings based on identified corrections on the design.
¨ Verified and validated design input,
vendor documents and technical information for correctness and adequacy based on defined standard requirements. Coordinated
to the contractor/vendor/client in writing on the matter of discrepancies and lacking information necessary to proceed in
the execution of works.
Management
¨ As a liaison, between JGC Yokohama
Japan and JGC Philippines, handled all inquiries, comments, and deviations concerning information. Prepared coordination correspondence
for other disciplines for clarifications.
¨ Organized and maintained an updated
master list of vendor drawings, control documents, transmittal, and various correspondences.
¨ Assured that all information issued
is the latest revisions, adequate, clear and accurate to keep a high quality of business.
¨ Reviewed and checked fabrication drawings
of various steel structures ensuring all details are in order against the design detailed drawings prior to release to fabrication.
Junior Engineer
Various projects
Design Engineering
¨ Prepared analysis and detailed design
calculations and drawings for both reinforced concrete and steel structures in accordance to project standards and specifications
at required schedule. These includes the following:
1. Various types of foundations ranging from combined or mat footings,
irregular shaped, piled, ring wall, sleepers and with socket type pedestals.
2. Concrete structures that includes bridge culvert, retaining walls,
water treatment tanks and pits.
3. Steel structures from platforms, walkways, pipe bridges and supports.
¨ Provided assistance in the preparation
of underground/ foundation location plan drawings. Took part in the sewer drain analysis and design of various projects.
Projects involved
as a Design Engineer:
|
Project Title |
Location |
Client |
|
Turkmenistan Polypropylene & Utility Project |
Turkmenbashi, TURKMENISTAN |
Turkmenneftegas
|
|
Malaysia LNG Tiga Plant
Project |
Bintulu Sarawak, MALAYSIA |
PETRONAS MLNG Tiga
|
|
BPC Polyethylene Plant Project (Area C5/C6 Modification) |
Bataan, Philippines |
Bataan Polyethylene Corp. (BPC) |
|
Pryce Gas Project |
Davao & Misamis, Philippines
|
Pryce Gases Inc. |
|
Cerro Negro Upgrader Project |
Cerro Negro, VENEZUELA |
MOBIL, PDVSA |
|
Port Dickson LRCC Project |
Port Dickson,
MALAYSIA |
SHELL Refining Company |